Performance Degradation Tracker

Every plant drifts from the machine that passed its acceptance test. This tracker quantifies the drift — in output, in heat rate, and in the only unit management never ignores: extra fuel burned per day.

The Calculation, Explained

What degradation is — and is not

Degradation is the loss of corrected performance between two points in a machine's life:

Output degradation % = ( Pcurrent,corr − Pbaseline,corr ) / Pbaseline,corr × 100
Heat-rate degradation % = ( HRcurrent,corr − HRbaseline,corr ) / HRbaseline,corr × 100

The word corrected does all the work in those formulas. Both points must first be corrected to the same reference conditions — otherwise you are comparing a July afternoon with a January morning and calling the weather "wear". Get both points corrected with the Performance Correction Calculator, then come back here.

Recoverable and non-recoverable

Assumptions and applicability

Worked example (the defaults above)

Baseline (acceptance test, corrected): 420.0 MW at 9,866 kJ/kWh. Today, 8,500 operating hours later, corrected: 402.5 MW at 10,240 kJ/kWh. Output degradation = −4.17% (17.5 MW missing); heat-rate degradation = +3.79%; rates of −0.49% and +0.45% per 1,000 hours. The fuel penalty at today's output: 402,500 kW × 24 h × 374 kJ/kWh = ≈ 3,613 GJ (3,424 MMBTU) of extra fuel every day — the number that turns a performance discussion into a maintenance-budget approval.

Practitioner's note. When degradation appears suddenly, suspect the measurements before the machine: a drifting inlet-temperature sensor manufactures "degradation" more reliably than any fouled compressor. Check instrument plausibility first — it is the cheapest overhaul you will ever do.

References

ASME PTC 46 / PTC 22 (correction methodology prerequisite); ISO 2314 (acceptance tests and degradation allowances in gas turbine contracts).

Related reading: What a Performance Test Really Proves.